If 36 persons are engaged on a piece of work, the work can be completed in 40 days. After 32 days, only 3/4 th of the work was completed. How many more persons are required to complete the work on time?

Asked on by | Votes 24 | Views: 1276 | Tags: ibps     | ibps po     | ibps po 2014     | time and work     | quantitative aptitude     | Add Bounty



If 36 persons are engaged on a piece of work, the work can be completed in 40 days. After 32 days, only 3/4 th of the work was completed. How many more persons are required to complete the work on time?
1). 10
2). 8
3). 9
4). 12

IBPS Books


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

31 vote
Answered by on | Votes 31 |
Solution

Remaining work = $\frac{1}{4}$
Remaining time = 8 days
Work done by 36 persons in 1 day = $\frac{1}{40}$
Work done by 1 person in 1 day = $\frac{1}{36 \times 40}$
Let the number of persons required to finish the remaining work be 'x'
$8 \times x \times \frac{1}{36\times40} = \frac{1}{4}$
$x = 45$
Number of additional persons = 45 - 36 = 9

Accepted Answer

Join Telegram Group




2 vote
Answered by on | Votes 2 |
Solution

Remaining work = $\frac{1}{4}$
Remaining time = 8 days
Work done by 36 persons in 1 day = $\frac{1}{40}$
Work done by 1 person in 1 day = $\frac{1}{36 \times 40}$
Let the number of persons required to finish the remaining work be 'x'
$8 \times x \times \frac{1}{36\times40} = \frac{1}{4}$
$x = 45$
Number of additional persons = 45 - 36 = 9




Other Questions

1.  Twelve men and six women together can complete a piece of work in four days. The work done by a women in one day is half the work done by a man in one day. If 12 men and six women started working and

2.  A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is

3. A and B undertook to do a piece of work for Rs. 48,000. A could do it alone in 5 days and B could do it alone in 8 days. With the help of C and D, they finished the work in 3 days. If the work done by C was twice that of the work done by D, then the difference between the shares of A and C was:

4. Rahi is 30% less efficient than Tanu. If Tanu does a work in 99 days, in how many days will they together complete a work?

5.  A take twice as much time as B or thrice as much time to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in?

6. Two pipes P and Q can fill an empty tank in 25 hours and 20 hours respectively. Pipe R alone can empty the completely filled tank in 50 hours. Firstly both the pipes P and Q are opened and after 8 hours pipe R is also opened. What will be the total time (in hours) taken to completely fill the tank?

7. M takes 60% more time than N to complete a wall. If together they complete the wall in 24 days, then how many days will N alone take to complete it?

8.  A can do piece of work in 15 days and B in 20 days they finished the work with the assistance of c in 5 days and got Rs.45 as their wages find the share for each in wages?

9. Working efficiencies of P and Q for completing a piece of work are in the ratio 3:4. The number of days to be taken by them to complete the work will be in the ratio

10. Ramesh can complete a work in 15 days and along with Geeta, he completes the same work in 6 days. If Geeta along with Rajan takes 9 days to complete the same work, time taken by Rajan alone to complete the same work is …….. days.