Rahim does \(\frac{7}{{10}}\) of a work in 21 hours. He then calls in Bablu and they together finish the remaining work in 6 hours. How long Bablu alone would take to do the whole work?

Asked on by | Votes 0 | Views: 24 | Tags: time and work     | quantitative aptitude     | Add Bounty

Rahim does \(\frac{7}{{10}}\) of a work in 21 hours. He then calls in Bablu and they together finish the remaining work in 6 hours. How long Bablu alone would take to do the whole work?


1). \(63\frac{1}{3}\) hours
2). 75 hours
3). 60 hours
4). 56 hours


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

Rahim does (7/10) part of a work in = 21 hours

∴ Rahim completes the work in = 21 × (10/7) hours = 30 hours

∴ Part of work Rahim can do in an hour = 1/30

Remaining part of the work = 1 – (7/10) = 3/10

Bablu and Rahim together done 3/10th part of the work in 6 hours

∴ Bablu and Rahim can complete the work = 6 × (10/3) hours = 20 hours

∴ Part of work Bablu and Rahim can do in an hour = 1/20

∴ Part of work Bablu alone can do in an hour

= Part of work Bablu and Rahim can do in an hour – Part of work Rahim can do in an hour

= (1/20) – (1/30)

= 1/60

∴ Bablu alone can complete the work in 60 hours

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+5)
Submit:

Other Questions

1. Two pipes X and Y can fill the cistern in 49 ½ minutes and 27 minutes respectively. Both pipes are opened. The cistern will be filled in 22 minutes, if pipe Y is closed after: 

2. If 15 person can do a job in 30 days, then 30 persons with twice the efficiency can do the same job in how many days?

3.  A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is

4. A can do a work in 20 days and B in 10 days. If they work on it together for 5 days, then what fraction of work is left.

5. Anju and Bablu can do a job together in 18 days. Anju is \(3\frac{2}{3}\) times more efficient than Bablu. The same job can be done by Bablu alone in

6. If Kavita is 70% more efficient than Savita and 50% less efficient than Babita, Savita is what percent less efficient than Babita?

7. X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part of the total work

8. 5 men can do a piece of work in 6 days while 10 women can do it in 5 days. In how many days can 5 women and 3 men do it ?

9.  12 men can complete a work in 6 days. 8 women can do it in 12 days. If 6 men and 8 women are employed together, work will be completed in

10. A and B can finish a job in 10 days while B and C can do it in 18 days. A started the job, worked for 5 days then B worked for 10 days and the remaining job was finished by C in 15 days. In how many days could C alone have finished the whole job?