The unit measurement for concrete work in RCC is in

Asked on by | Votes 64 | Views: 1890 | Tags: estimating     | cost and valuation     | civil engineering     | Add Bounty

The unit measurement for concrete work in RCC is in
1). Meter
2). Square Meter
3). Cubic Meter
4). Square Centimetre


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

24 vote
Answered by on | Votes 24 |

The principle of units of measurements normally consists the following:

a) Single units work like doors, windows, trusses etc., are expressed in numbers.

b) Works consists linear measurements involve length like cornice, fencing, hand rail, bands of specified width etc., are expressed in running metres (m).

c) Works consist of areal surface measurements involve area like plastering, white washing, partitions of specified thickness etc., and are expressed in square meters (m2)

d) Works consists cubical contents which involve volume like earth work, cement concrete, Masonry etc. are expressed in Cubic metres (m3).