The change in cost of built-up facilities with the change in size of the project of similar type is known as
1). Time reference cost estimate
2). Cost capacity factor
3). Life cycle cost
4). Unit cost estimate
Cost capacity factor
The factor that accommodate the change in cost of built-up facilities with the change in size of the project of similar type is called as cost capacity factor.
If C1 and C2 be the cost of facilities to be built and old facilities and their size be Q1 and Q2 respectively. Then the cost of the new facility is calculated as
$({C_1} = {C_2}{\left( {\frac{{{Q_1}}}{{{Q_2}}}} \right)^x})$
where x is called the capacity factor.4. The measurement is made in square metre in case of
6. The number of steps in a flight generally should not be less than
8. The slope of a ramp should not be more than:
9. Composting and lagooning are the methods of
10. The minimum strength of the mortar used in load bearing brick masonry, is