Which of the following is not a type of methods of preliminary estimate?
1). Time referenced cost estimate
2). Cost capacity factor
3). Installation cost ratio
4). Procurement cost factor
Procurement cost factor is not a method of preliminary estimate.
Preliminary Estimate
The preliminary estimate is obtained during early phases of project.
As the project progresses, an estimate keeps on getting refined and lastly, we get definitive estimate.
Different methods of preliminary estimate can be grouped into the following categories
2. The standard length of rail for Broad Gauge and Meter Gauge are respectively
4. PERT is
5. The Auger borings are not common
7. A circular column section is generally not used in actual practice because
8. According to ISI method of measurement, the order of the sequence is
9. The compaction of concrete in the drilled pile hole is done by compressed air in the case of