A,B and C together earn Rs. 450 per day, while A and C together earn Rs.310 and Band C together earn Rs.260. The daily earning of C is 

Asked on by | Votes 0 | Views: 23 | Tags: time and work     | quantitative aptitude     | Add Bounty

A,B and C together earn Rs. 450 per day, while A and C together earn Rs.310 and Band C together earn Rs.260. The daily earning of C is 
1). 195
2). 190
3). 140
4). 120


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |

A + B + C = 450        -----(i)

A + C = 310        -----(ii)

B + C = 260        -----(iii)

From Eqs.(i) and (ii)

B = [450 – 310] = 140

From Eq.(iii)

C = [260 – 140] = 120

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+3)
Submit:

Other Questions

1. If A is 6 times more than B, then by what percentage is B is less than A?

2.  2 men and 8 women can earn 713640 in 11 days. 6 men and 10 women can earn 713 800 in 15 days. In how many days will 10 men and 15 women earn 78700 ?

3.  A and B can do a work in 18 day, B and C in 30 days, A and C in 22 (1/2) days. In how many days can A,B and C individually do the work?

4. A and B working together, can do a piece of work in $4\frac{1}{2}$ hours, B and C working together can do it in 3 hours, C and A working together can do it in $2\frac{1}{4}$ hours. All of them begin the work at the same time. find how much time they will take to finish the piece of work.

5. A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how much time will A and B, working together, finish the work?

6. Raj and Rahul’s work efficiency is in the ratio 3∶ 2. If Raj can do a work in 12 days, in how many days will Rahul do the work alone?

7. A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

8. Given below are two quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers. Quantity A: M can finish a work in 12 days and N can d

9. A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How, many persons were originally there ?

10. A and B together can do a piece of work in 10 days. A alone can do it in 30 days. The time in which B alone can do it is