P can do a work in 10 days. Q can do the same work in 15 days. If they work together for 5 days, how much of the work will they complete?

Asked on by | Votes 0 | Views: 23 | Tags: time and work     | quantitative aptitude     | Add Bounty

P can do a work in 10 days. Q can do the same work in 15 days. If they work together for 5 days, how much of the work will they complete?
1). 1/2
2). 2/3
3). 1/3
4). 5/6


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

Work done by P in 1 day = 1/10

Work done by Q in 1 day = 1/15

Work done by P and Q together in 1 day = 1/10 + 1/15 = 1/6

∴ work done by P and Q together in 5 days = 1/6 × 5 = 5/6

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+3)
Submit:

Other Questions

1. 8 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to flnish the work. In how many days will 12 men finish the same work ?

2. 5 class A workers and 4 class B workers are assigned a job to paint a circular park. They work for one day and complete painting till half the radius of the circular park. The next day, class B workers go on strike and returns the day after as the management resolves their problems. This creates a delay of 4 hours and 48 min in overall. If their payment is based on their efficiency, what will be the ratio of their pay?

3.  P can complete work in 12 days working 8 hrs a day. Q can complete the same work in 8 days working10 hrs a day. If both P and Q working 8 hrs a day in how many days can they complete the work?

4. In a house, there are six 40 W lamps which are switched on for 5 hours a day and three 80 W fans which are switched on for 10 hours a day. If electricity costs Rs.2 per kilowatt hours. What is the monthly electricity bill?

5.  A and B together can do a piece of work in 12 days, which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In how many days C a

6.  Fill a tank individually in 10 min & 20 min. However, there is leakage at bottom which can empty a filled tank in 40 min. If the tank is empty, how much time both the taps take to fill the tank?

7.  A can do a piece of work in 10 days and B can do the same work in 12 days. A and B worked together for 2 days. How many more days are required to complete the remaining work if they work together?

8. 6 men or 12 women can do a piece of work in 20 days. In how many days can 8 men and 16 women do twice as big as this work ?

9. If there is a reduction In the number of workers in a factory in the ratio 15:11 and an increment in their wages in the ratio 22:25, then the ratio by which the total wages of the workers should be decreased is

10. A can complete the whole work in 18 days alone when A is assisted by B, they can complete the whole work in 12 days, When B is assisted by C, B and C together can complete the work in 9 days, if A get an amount of Rs. 500, then find the amount received by C.