In which of the following the contractor undertakes the execution or construction of a specific work with all its contingencies, to complete it in all respect within a specified time for fixed amount?
1). Item rate contract
2). Lump sum contract
3). Percentage rate Contract
4). Schedule contract
Lump Sum Contract:
In this type of contract, the contractor undertakes the execution or construction of a specific work with all its contingencies, to complete it in all respect within a specified time for fixed amount.
The contract agreement in lump sum contract includes: