Pradeep has done 1/4th of a job in 14 days, Saquib completes the rest of the job in 56 days. In how many days can they together complete the job?
We know that,
Work done = Efficiency × Time taken
Let’s assume the total work done to be ‘1’, Pradeep’s efficiency be ‘P’ and Saquib’s efficiency be ‘S’
According to the given information,
⇒ P × 14 = ¼
⇒ P = 1/56
⇒ S × 56 = ¾
⇒ S = 3/224
If they work together, let’s assume they take ‘T’ days.
⇒ (P + S) × T = 1
⇒ (1/56 + 3/224) × T = 1
⇒ ((4 + 3)/224) × T = 1
⇒ T = 224/7
∴ T = 32 days