Pradeep has done 1/4th of a job in 14 days, Saquib completes the rest of the job in 56 days. In how many days can they together complete the job?

Asked on by | Votes 0 | Views: 1413 | Tags: time and work     | quantitative aptitude     | Add Bounty

Pradeep has done 1/4th of a job in 14 days, Saquib completes the rest of the job in 56 days. In how many days can they together complete the job?


1). 64 days
2). 32 days
3). 16 days
4). 8 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

We know that,

Work done = Efficiency × Time taken

Let’s assume the total work done to be ‘1’, Pradeep’s efficiency be ‘P’ and Saquib’s efficiency be ‘S’

According to the given information,

⇒ P × 14 = ¼

⇒ P = 1/56

⇒ S × 56 = ¾

⇒ S = 3/224

If they work together, let’s assume they take ‘T’ days.

⇒ (P + S) × T = 1

⇒ (1/56 + 3/224) × T = 1

⇒ ((4 + 3)/224) × T = 1

⇒ T = 224/7

∴ T = 32 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+1)
Submit:

Other Questions

1. Two pipes can fill a cistern in 25 min and 20 min respectively. A third pipe can empty it in 10 minutes. Find out how much time will it take to empty a filled cistern? 

2.  A and B complete a work in 6 days. A alone can do it in 10 days. If both together can do the work in how many days?

3. A tank has a leak which would empty the completely filled cistern in 20 hours. If the tank is full of water and a tap is opened which admits 2 liters of water per minute in the tank, the leak now takes 30 hours to empty the tank. How many liters of water does the tank hold?

4.  Ram and Shyam together can finish a job in 8 days. Ram can do the same job on his own in 12 days. How long will Shyam take to do the job by himself?

5.  A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days?

6. If A and B together do a job in 7.5 days and if A could do the job in 10 days if he worked alone. How many days would B take to do the job if he worked alone? 

7. If 8 men or 12 boys can do a piece of work in 16 days, the number of days requiredto complete the work by 20 men and 6 boys is

8. Three men P, Q and R working individually can finish a job in 13, 17 and 19 days respectively. They decided to work together but after 3 days, P left and after another one day, Q also left and the remaining work was completed by R. If they got Rs. 1,00,000 collectively for the entire work, what will be the lowest share?

9. A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?

10. Running at the same constant rate, 6 identical machines can produce a total of 270 balls per 3 minutes. At this rate, how many balls could 10 such machines produce in 2 minutes?