Which of the following is NOT applicable in contracts as far as security deposit is concerned?

Asked on by | Votes 27 | Views: 163 | Tags: estimating     | cost and valuation     | civil engineering     | Add Bounty

Which of the following is NOT applicable in contracts as far as security deposit is concerned?
1). Amount can be withheld from any other contract with the same client
2). Necessary before entering into a contract
3). Refundable after maintenance period
4). Amount depends on tendered amount


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

26 vote
Answered by on | Votes 26 |

When contract security is required, the contractor may, in lieu of a performance bond and a labor and material payment bond, provide a security deposit.

When a security deposit is delivered, it must be, in the amount of 10% of the contract price for construction contracts and at least 10% for other contract types.

Security deposit is always refundable in nature.

Security deposit cannot be withheld from any other contract with the same client.

Accepted Answer

Join Telegram Group




0 vote
Answered by on | Votes 0 |

Security deposit cannot be withheld from any other contract with the same client.