For 15 mm thick cement plastering 1 : 6 on 100 sq. m. new brick work, the quantity of cement required is

Asked on by | Votes 59 | Views: 6335 | Tags: estimating     | cost and valuation     | civil engineering     | Add Bounty

For 15 mm thick cement plastering 1 : 6 on 100 sq. m. new brick work, the quantity of cement required is
1). 0.200 m3
2). 0.247 m3
3). 0.274 m3
4). 0.343 m3


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

59 vote
Answered by on | Votes 59 |

The volume of the plaster = 100 m2 × 0.015 m = 1.5 m3

We have to increase the mortar value by (To accommodate new wall depression & wastages volume of plaster)

Increase mortar for uniform wall by 30-35%

For volume of dry mortar increase 25%

So, it is possible to go around 60% extra volume for dry & wet mortar.

Therefore, volume of dry mortar = $(1.5 \times \frac{{160}}{{100}} = 2.4)$

Now 1 part is of cement has 6 part is of sand so,

Cement = (1/7) × 2.4 = 0.343 m3
Accepted Answer

Join Telegram Group




30 vote
Answered by on | Votes 30 |
1.5×1.54×1/7=.33