Three men and 5 women together can finish a job in 3 days. Working on the same job 3 women take 5 days more than the time required by 2 men. What is the ratio of efficiency of a man to a woman?

Asked on by | Votes 44 | Views: 2633 | Tags: time and work     | quantitative aptitude     | Add Bounty

Three men and 5 women together can finish a job in 3 days. Working on the same job 3 women take 5 days more than the time required by 2 men. What is the ratio of efficiency of a man to a woman?
1). 2 : 1
2). 3 : 2
3). 5 : 2
4). 4 : 1


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

43 vote
Answered by on | Votes 43 |

According to the question,

Three men and 5 women together finished the job in 5 days

Let, required no. of days by 2 men = x

⇒ Efficiency of 1 man = 2x

⇒ Required no. of days by 3 women = x + 5

⇒ Efficiency of 1 woman = 3x + 15

Let the total work be 90 units

⇒ 3M + 5W = 90/3 = 30 units

⇒ Work of 1 man = 90/2x units = 45/x

⇒ Work of 1 woman = 90/(3x + 15) units = 30/(x + 5)

So,

⇒ 3(45/x) + 5[30/(x + 5)] = 30

⇒ 45x + 225 + 50x = 10(x + 5)x

⇒ 2x2 - 9x - 45 = 0

⇒ (2x - 15) (x + 3) = 0

⇒ x = 15/2, -3

Since, -3 cannot be possible

⇒ x = 15/2

⇒ Work of 1 man = 45/7.5

⇒ Work of 12 woman = 30/12.5

⇒ Ratio = 45/7.5 : 30/12.5 = 5 : 2

∴ Ratio of man and woman is 5 : 2
Accepted Answer

Join Telegram Group




Other Questions

1. 30 men can repair a road in 18 days. They are Joined by 6 more workers. Now the road can be repaired in

2. Six women alone can complete a piece of work in 10 days whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work ?

3.  If 32 men and 24 days can reap a field in 9 days in how many days will 28 men and 12 boys reap it supposing that 4 men can do as much as 6 boys?

4.  Sixty men can stitch 200 shirts in 30 days working 8 hours a day. In how many days can 45 men stitch 300 shirts working 6 hours a day?

5.  When A, B and C are deployed for a task , A and B together do 70% of the work and B and C together do 50% of the work. who is most efficient?

6.  A can do half the work in one day where as B can do it full. B can also do half the work of C in one day. Ratio in their efficiency will be?

7. Raja can do a piece of work in 20 days while Ramesh can finish it in 25 days. Ramesh started working and Raja joined him after 10 days. The whole work is completed in

8. A and B can complete a task together in 6 days. C and D can together complete the same task in 12 days. If A, B, and C together complete the task in 5 days, in how many days will D complete the task alone?

9.  A contractor decided to build a bridge in 35 days. He employed 60 men in the beginning and 40 more after 17 days and completed the work on time. If he had not employed the additional men, how many day

10. P is twice as good as Q and together they finish a piece of work in 36 days. The number of days taken by P alone to finish the work?