A swimming pool has 3 pipes to drain off the water. The first two pipes A and B, operating simultaneously, can empty the pool in 9/16 the time than that taken by C alone. Pipe A, working alone, takes one third the time taken by pipe B. All of them together take 2 hrs 24 minutes to empty the pool. Time taken by pipe A to empty the pool in hours is

Asked on by | Votes 0 | Views: 218 | Tags: time and work     | quantitative aptitude     | Add Bounty

A swimming pool has 3 pipes to drain off the water. The first two pipes A and B, operating simultaneously, can empty the pool in 9/16 the time than that taken by C alone. Pipe A, working alone, takes one third the time taken by pipe B. All of them together take 2 hrs 24 minutes to empty the pool. Time taken by pipe A to empty the pool in hours is
1). 5
2). 10
3). 15
4). 20


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

Let the efficiencies of the three pipes be a, b and c.

As the first two pipes A and B operating simultaneously can empty the pool in 9/16 the time than that taken by C alone

⇒ (a + b)/c = 16/9                                                                  - - - - - - - - - - - - - - - (i)

Pipe A, working alone, takes one third the time taken by pipe B

⇒ a/b = 3                                                                                - - - - - - - - - - - - - - - (ii)

2hr 24min = 2 + 24/60 hr = 2 + 2/5 hour = 12/5 hr

Together they can empty the pool in 12/5 hr

⇒ (a + b + c) × 12/5 = 1                                                          [Using (ii)]

⇒ (a + a/3 + (a + b) × 9/16) × 12/5 = 1                                  [Using (i)]

⇒ (a + a/3 + (a + a/3) × 9/16) × 12/5 = 1                               [Using (ii)]

⇒ (a + a/3 + 4a/3 × 9/16) × 12/5 = 1

⇒ (a + a/3 + 3a/4) = 5/12

⇒ a(12 + 4 + 9)/12 = 5/12

⇒ a = 1/5

Since the efficiency of pipe A is a, the time taken by A alone = 1/a = 5 hours

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+2)
Submit:

Other Questions

1. P and Q can do a project in 20 and 12 days respectively. In how many days can they complete 40% of the project if they work together?

2. Mansukh can do a piece of work in 10 hours. If he is joined by Jayanti who is 50% more efficient, in what time will they together finish the work?

3.  A certain number of men can do a work in 40days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially?

4. While working 7 hours a day. A alone can complete a piece of in 6 days and B alone in 8 days. In what time would they complete it together, working 8 hours a day ?

5. 2 children and 3 men can do a work in 12 days while 3 children and 2 men can do the same work in 10 days. How many days it will take to complete the same work if 1 child and 1 man work together?

6.  ‘A’ can complete a piece of work in 12 days ‘A’ and ‘B’ together can complete the same piece of work in 8 days. In how many days can ‘B’ alone complete the same piece of work?

7. A and B together can complete a piece of work in 10 2/7days white B and C together can complete the same work in 13 1/3 days. B is 25% more efficient than C. In how many days will A and C together complete the same work ?

8.  A and B can do a job in 10 days. B and C can do the same job in 15 days. If all three worked together complete the work in 6 days, then in how many days can B complete the whole job?

9. Aman and Barkha together work for 6 days and leave the job. Chandan can do the whole work in 30 days. If the ratio of their efficiency is 3 : 6 : 2, then in how many days can Chandan alone finish the remaining work?

10. A can complete $\frac{2}{3}$ of a work in 4 days and B can complete $\frac{3}{5}$ of the work in 6 days. In how many days can both A and B together complete the work ?