A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a day

Asked on by | Votes 0 | Views: 69 | Tags: time and work     | ssc cgl tier 1 11 08 2017 shift 3     | ssc cgl tier 1     | ssc cgl     | quantitative aptitude     | ssc cgl tier 1 2017     | ssc cgl 2017     | Add Bounty

A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a day
1). 4
2). $5\frac{4}{11}$
3). $6\frac{4}{11}$
4). $4\frac{4}{11}$


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |
Its very simple question $4\frac{4}{11}$ is the correct answer.

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+4)
Submit:

Other Questions

1. A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

2. A woman works continuously for 7 days in the kitchen and refuses to work on the 8th day when her husband takes over. If she starts her work on a Sunday, the 11th time she rests will be on which day of the week?

3. A is 30% more efficient than B, and can alone do a work in 23 days. The number of days, in which A and B, working together can finish the Job is

4. Nirmit can do $\frac{2}{3}$ of a job in 18 days. Kashish is twice as efficient as Nirmit. In how many days Kashish will complete the job?

5.  X completes a job in 2 days and Y completes it in 3 days and Z takes 4 days to complete it. If they work together and get Rs. 3900 for the job, then how much amount does Y get?

6.  Two pipes A & B can fill a tank in 80 min & 60 min.. There is also an outlet C. If all three pipes are opened together, the tank takes 40 min to fill completely. How much time will C take to empty the

7. 2 men and 3 women undertook a piece of work for Rs. 12,000. 2 men can do the work in 12 days and 3 women can do the same work in 15 days. With the assistance of 5 children, they finished the work in 5 days. What is the share of 1 child?

8. 10 men can complete a piece of work in 34 days, 16 women can complete the same piece of work in 56 days. 5 men and 18 women work together for 20 days. If only women were to complete the remaining piece of work in 4 days along with a boy who does 10 units of work per day, how many women would be required?

9.  'A' is twrice as fast as 'B' , and is therefore able to finish a work in 24 days less than 'B' . What is the time in which they can do it working together ?

10. Amit and sujit together can complete an assignment of data entry in five days. Sujit?s speed 80% of Amit?s speed and the total key depressions in the assignment are 5,76,000. What is Amit?s speed in key depressions per hour if they work for 8 hours a day ?