 A can do a half of certain work in 70 days and B one third of the same in 35 days. They together will do the whole work in.

Asked on by | Votes 0 | Views: 2122 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can do a half of certain work in 70 days and B one third of the same in 35 days. They together will do the whole work in.

A). 420 days

B). 120 days

C). 105 days

D). 60 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

-3 vote
Answered by on | Votes -3 |

60 days



A = 140 days

B = 105 days

1/140 + 1/105 = 7/420 = 1/60


=>60 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+4)
Submit:

Other Questions

1. If x men can do a piece of work in x days, then the number of days in which y men can do the same work is

2.  What is the total number of units manufactured by Company C over all the years together ?

3.  If 'A' is thrice as fast as B, and is therefore able to finish a work in 40 days less than B, find the time in which they can do it working together.

4. A can do a certain Job in 12 days. B is 60% more efficient than A. To do the same Job B alone would take :

5. A is 25% more efficient then B. A works for ‘D’ days and completed 1/3 of work and left the work and remaining work is completed by B in ‘D + 12’ day. In how many days A and B together can complete the work.

6. P, Q and R undertook a work for Rs. 55000. Together P and Q complete (8/11)th part of the work. What is the share (in Rs) of R?

7. Azhar is 4 times as good a workman as Balaraj and therefore is able to finish a job in 45 days less than Balaraj. Working together, they can do it in:

8. Two pipes A and B, would fill a cistern in 20 and 30 minutes respectively. Both pipes being opened, find when the second pipe must be turned off so that the cistern may be just filled in 14 minutes?

9. A man undertakes to do a certain work in 150 days. He employs 200 men . He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is :

10.  A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C, when they work individually?