A can do a half of certain work in 70 days and B one third of the same in 35 days. They together will do the whole work in.
A). 420 days
B). 120 days
C). 105 days
D). 60 days
60 days
A = 140 days
B = 105 days
1/140 + 1/105 = 7/420 = 1/60
=>60 days