A and B together can do a work In 4 days. A alone can do it in 12days.what time B will take to do the work alone?
A).
6 days
B). 8 days
C). 12 days
D). 10 days
6 days
A and B 1day's work = 1/4
A alone can do 1day's work = 1/12
what time B will take to do the work alone?
B = (A+B) - A = (1/4) - (1/12) = 6 Days