Select the correct statement.

Asked on by | Votes 0 | Views: 23 | Tags: civil engineering     | construction planning and mgmt     | Add Bounty

Select the correct statement.

A).  Activity arrows in a CPM network are drawn to scale

B).  The tail of an arrow represents the finish of an activity

C).  Arrow bead represents the start of an activity

D).  None of the above


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

 None of the above