 A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

Asked on by | Votes 0 | Views: 26 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

A). 6 days

B). 12 days

C). 5 days

D). 9 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

6 days



B's 10 day's work = ( 1/15 x 10 ) = 2/3 .

Remaining work = ( 1 - 2/3 ) = 1/3 .

Now, 1/18 work is done by A in 1 day.

Therefore 1/3 work is done by A in ( 18 x 1/3 ) = 6 days.

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1.  A and B together can do a work in 6 days. If A alone can do the work in 10 days then in how many days can B alone do it ?

2. If Kavita is 70% more efficient than Savita and 50% less efficient than Babita, Savita is what percent less efficient than Babita?

3. A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs. 960 for the whole work how much money A gets?

4.  If the production of a factory grows at a rate of 8% p.a., what will be its production for the year 2006 if its production in 2004 was 60 lakh tonnes (Rounded off to two digits after decimal) ?

5. Painter 'A' can paint a house in 10 days and 'B' can do it in 20 days. With help of 'C', they did the job in 5 days only. Then, 'C' alone can do the job in:

6. .A can finish a work in 7 days . B can finish the same work in 9 days . The days required to finish the work by both of them together.

7. Two pipes together can fill a cistern in 36 hours. If another draining pipe attached to the tank, it takes 9 hours longer to fill the tank. Find in how much time can the drain pipe alone can empty a half full tank.

8.  A can do a piece of work in 12 days. When he had worked for 2 days B joins him. If the complete work was finished in 8 days. In how many days B alone can finish the work?

9. A school has 8 periods of 45 minutes each, every day. How long will each period be if the school has to have 9 periods everyday, assuming the working hours to be the same?

10. Pascal and Rascal are two workers. Working together they can complete the whole work in 10 hours. If the Pascal worked for 2.5 hours and Rascal worked for 8.5 hours, still there was half of the work to be done. In how many hours Pascal working alone, can complete the whole work?