 A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take t

Asked on by | Votes 0 | Views: 20 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take t

A). 18 days

B). 24 days

C). 30 days

D). 36 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

18 days



NA

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+5)
Submit:

Other Questions

1. Rashika can do a work in 5 days. Rashmi can do the same work in 7 days. Both of them finish the work together and they get Rs. 240 for the work. What is the share (in Rs.) of Rashika?

2. A and B can do a piece of work in 10 days B and C can do it in 12 days, C and A in 15 days. In how many days will C finish it alone ?

3. X is 3 times as fast as Y and is able to complete the work in 40 days less than Y. Then the time in which they can complete the work together is

4. Two men undertook to do a Job for Rs. 1400. One of them can do it alone in 7 days, and the other in 8 days. With the assistance of a boy they together completed the work in 3 days. How much money will the boy get ?

5. A, B and C together can do a piece of work in 40 days. After working with B and C for 16 days. A leaves and then B and c complete the remaining work in 40 days more. A alone could do the work in

6.  A certain number of men can do a work in 54days. If there were 6 men more it could be finished in 6 days less. How many men were there in the beginning?

7.  2 men 3 women and a boy can complete a job in 3, 4 and 12 days respectively. How many boys must assist one men one women to complete the job in 1/4 of a day?

8.  A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

9. 10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?

10. A is 30% more efficient than B, and can alone do a work in 23 days. The number of days, in which A and B, working together can finish the Job is