 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?

Asked on by | Votes 0 | Views: 24 | Tags: quantitative aptitude     | time and work     | Add Bounty

 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?

A). 35

B). 40

C). 45

D). 50


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

40



NA

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+4)
Submit:

Other Questions

1.  X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

2.  A and B can do a piece of work in 48 days, A and C can do it in 60 days, b and c can do it 72 days. In what time can c alone do it?

3.  P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they comp

4. Three men A, B and C working together can do a Job in 6 hours less time than A alone, in 1 hour less time than B alone and in one half the time needed by C when working alone.Then A and B together can do the Job in

5. A and B undertook to do a piece of work for Rs. 4500. A alone could do it 8 days and B alone in 12 days. With the assistance of C they finished the work in 4 days. Then C’s share of the money is

6. A company has 3 category of Labours, Category A, B and C. 1 Labour of Category A, 3 of B and 4 of C can do a piece of work in 96 hrs, 2 of A and 8 of C can do it in 80 hrs, 2 of A and 3 of B can do it in 120 hrs, 5 of A and 12 of C can do it in

7. P can complete a work in 15 days and Q in 24 days. They began the work together but Q left the work 2 days before its completion. In how many days was the work completed?

8.  Four pipes A,B, C and D can fill a cistern in 20,25, 40 and 50 hours respectively.The first pipe A was opened at 6:00 am, B at 8:00 am, C at 9:00 am and D at 10:00 am. when will the Cistern be full?

9. Amit can complete a work in 25 days and Punit can complete the same work in 20 days. Punit alone worked at it for 10 days and then left the work. In how many days will Amit alone complete the remaining work?

10. A is four times efficient as B. B started the work and after 6 days, A joined him. If the whole work was completed in 12 days, in how many days A alone can finish the whole piece of work ?