 28 men can complete a piece of work in 21 days. How many more men must be hired to complete the work in 14 days ?

Asked on by | Votes 1 | Views: 83 | Tags: quantitative aptitude     | time and work     | Add Bounty

 28 men can complete a piece of work in 21 days. How many more men must be hired to complete the work in 14 days ?

A). 12

B). 14

C). 16

D). 20


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

14



Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1. A and B can complete a task together in 6 days. C and D can together complete the same task in 12 days. If A, B, and C together complete the task in 5 days, in how many days will D complete the task alone?

2. Amar started doing a work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?

3.  A does 4/5th of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

4. P and Q can do a project in 150 and 100 days respectively. In how many days can they complete 60% of the project if they work together?

5. A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in

6.  A and B together can do a work in 6 days. If A alone can do the work in 10 days then in how many days can B alone do it ?

7.  A can do a work in 24 days and B can do it in 8 days. In how many days A and B can do the work?

8. A and B can do a piece of work in 15 days, B and C can do a similar work in 12 days and C and A in 10 days. How many days will A take to do the work by himself ?

9. A can do a certain Job in 12 days. B is 60% more efficient than A. To do the same Job B alone would take :

10. A and B together can complete a particular task in 4 days.If A alone can complete the same task in 6 days, how many days will B take to complete the task if he works alone ?