If 12 men and 16 boys can do a piece of work in 5 days and 13 men together will 24 boys can do it in 4 days. Compare the daily work done by a man with that of a boy.
A). 4:3
B). 2:1
C). 1:2
D). 2:5
2:1
12M + 16B ----- 5 days
13M + 24B ------- 4 days
60M + 80B = 52M + 96B
8M = 16B => 1M = 2B
M: B = 2:1