A and B working separately can so a 15 days respectively. If they work on alternate days begining with A , in how many days will the work be completed ?

Asked on by | Votes 0 | Views: 26 | Tags: time and work     | quantitative aptitude     | ssc cpo 2003     | Add Bounty

A and B working separately can so a 15 days respectively. If they work on alternate days begining with A , in how many days will the work be completed ?
1). 18 days
2). 13 days
3). 12 days
4). 6 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |
i think option 3 is correct

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+4)
Submit:

Other Questions

1. A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?

2.  30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers required to finish the same piece of work in 30 days will be

3. Work done by 1 man is equal to the work done by 4 children and work done by 1 woman is equal to the work done by 2 children. 2 men, 2 women and 1 child can complete work together in 8 days. In how many days 4 men, 4 women and 2 children can complete the work?

4. 2 men and 3 women can do a piece of work in 10 days while 3 men and 2 women can do the same work in 8 days. Then , 2 men and 1 women can do the same work in

5. A and B together can do a work in 10 days, B and C together can do the same work in 6 days, A and C together can do the work in 12 days. Then A, B and C together can do the work in

6.  Ashokan is thrice as good a workman as Nitin and is therefore able to finish a piece of work in 40 days less than Nitin. Find the time in which they can do it working together.

7. 3 men or 4 women can complete a job in 120 days. 12 men and 16 women will complete the same job in how many days?

8. 4 men and 6 women get Rs. 2400 by doing a piece of work in 5 days. 3 men and 7 women get Rs. 2760 by doing the same work in 6 days. In how many days, 7 men and 6 women can complete the same work getting Rs. 5280?

9. A man, a woman and a boy can complete a job in 3, 4 and 12 days respectively. How many boys must assist 1 man and 1 woman to complete the job in $\frac{1}{4}$ of a day ?

10. A garrison has provisions for few days. After 15 days,1/4 of people left and it was found that the provisions would last for as long as before. How long was that?