A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time, then B left the work. If A completed the rest of the work in 10 days, then B worked for

Asked on by | Votes 0 | Views: 48 | Tags: time and work     | quantitative aptitude     | ssc cgl tier 1 2008     | Add Bounty

A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time, then B left the work. If A completed the rest of the work in 10 days, then B worked for
1). 6 days
2). 8 days
3). 12 days
4). 16 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

3 vote
Answered by on | Votes 3 |
option 1 is the right answer

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+3)
Submit:

Other Questions

1. Working 5 hours a day, A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

2. A garrison of 160 men has provision for 40 days. At the end of 10 days, 40 more men joined them. How many days could the soldiers sustain themselves if they had joined on the first day itself?

3.  Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two differ

4. A and B working together, can do a piece of work in $4\frac{1}{2}$ hours, B and C working together can do it in 3 hours, C and A working together can do it in $2\frac{1}{4}$ hours. All of them begin the work at the same time. find how much time they will take to finish the piece of work.

5. A can do a piece of work in 4 hours; B and C can do it in 3 hours, A and C can do it in 2 hours. How long will B alone take to do it ?

6. A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs. 960 for the whole work how much money A gets?

7.  A can complete a piece of work in 12 days and B is 60% more efficient than A. In how many days B will complete the same work?

8. A can do 75% of a job in 18 days and B can do 25% of the job in 12 days. If they work on it together, in how many days can they do 75% of the job?

9. Mahanath works 2 times as fast as Sahay. If Sahay can complete a job alone in 21 days, then in how many days can they together finish the job?

10.  If 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is?