If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it ?

Asked on by | Votes 0 | Views: 47 | Tags: time and work     | quantitative aptitude     | ssc cgl tier 1 2003     | Add Bounty

If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it ?
1). 10 days
2). 11 days
3). 9 days
4). 12 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

3 vote
Answered by on | Votes 3 |
is option 4 is the correct answer?? am i right?

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+1)
Submit:

Other Questions

1.  The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them to finish the work are in the ratio:

2. Anju and Bablu can do a job together in 18 days. Anju is \(3\frac{2}{3}\) times more efficient than Bablu. The same job can be done by Bablu alone in

3. Gaurav is 4 times as good a workman as Vaibhav and therefore is able to finish a job in 60 days less than Vaibhav. How many days both will take finish the same task?

4.  A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C, when they work individually?

5. Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work than when work together. If B worked alone, would take $4\frac{1}{2}$ hours more than when work together. The time required to finish the work together is

6. 75 boys finish a work in 24 days. How many men will complete thrice the work in 15 days while 2 men do in a day same work as 3 boys do in a day?

7.  A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days A do the work if he is assisted by B and C on every third day?

8. A does 50% of a work in 12 days. He then calls in B and they together finish the remaining work in 8 days. How long B alone would take to complete the whole work?

9. If 8 men or 12 women can do a piece of work in 25 days, in how many days can the same work be done by 6 men and 11 women?

10.  A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :