3 men and 4 boys can complete a piece of work in 12 days. 4 men and 3 boys can do the same work in 10 days. Then 2 men and 3 boys can finish the work in number of days is
3 men and 4 boys can complete a piece of work in 12 days. 4 men and 3 boys can do the same work in 10 days. Then 2 men and 3 boys can finish the work in number of days is 1). $17\frac{1}{2}$ days 2). $5\frac{5}{11}$ days 3). 8 days 4). 22 days