A can complete a work in 6 days while B can complete the same work in 12 days. If they work together and complete it, the portion of the work done by A is
A can complete a work in 6 days while B can complete the same work in 12 days. If they work together and complete it, the portion of the work done by A is 1). $\frac{1}{3}$ 2). $\frac{2}{3}$ 3). $\frac{1}{4}$ 4). $\frac{1}{2}$