A is thrice as good a workman aa B and is, therefore, able to finish a piece of work in 60 days less than B.The time (in days) in which they can do it working together is

Asked on by | Votes 0 | Views: 39 | Tags: time and work     | quantitative aptitude     | ssc cpo 1999     | 2005     | 2011     | 2012     | Add Bounty

A is thrice as good a workman aa B and is, therefore, able to finish a piece of work in 60 days less than B.The time (in days) in which they can do it working together is
1). 22 days
2). $22\frac{1}{2}$ days
3). 23 days
4). $23\frac{1}{4}$ days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |
option 2 : - $22\frac{1}{2}$ days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+5)
Submit:

Other Questions

1.  A, B and C can do a piece of work in 11 days, 20 days and 55 days respectively, working alone. How soon can the work be done if A is assisted by B and C on alternate days?

2. A can complete a work in 20 days and B can complete the same work in 25 days. If both of them work together, then in 3 days what percent of the total work will be completed?

3. Having the same capacity 6 taps fill up a water tank in 36 min. How many taps of the same capacity required to fill up the same water tank in 8 min?

4. A can finish a work in 30 days working 16 hours a day. B can finish the same work in (80/3) days working 18 hours a day. Find in how many days A and B together can finish the same work, if A and B work 20 hours a day?

5.  A can do a piece of work in 12 days. When he had worked for 2 days B joins him. If the complete work was finished in 8 days. In how many days B alone can finish the work?

6. A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days, how much of work is left ?

7. A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

8.  A takes 10 hours to do a work. B takes 12 hours to do the same works. In how many hours A & B working together will complete the work?

9. If the work done by (x - 1) men in (x + 1) days is to the work done by (x + 2) men in (x - 1) days is in the ratio of 5 : 6, then x is equal to

10. Working together, A and B can complete a given task in 24 days. If the efficiencies of A and B are in the respective ratio of 3 ∶ 2, in how many days can B complete half of the task?