ExamCompetition Forum Question Papers Ask A Question Mock Test Learn & Earn Sign Up Login Menu



0 vote

A and B together can complete a work in 24 days. B alone does 1/3rd part ofthis work in 12 days. How many days will A alone take to complete the remaining work?

Asked on by | Votes 0 | Views: 26 | Tags: ssc     | ssc cgl     | ssc cgl tier 1     | ssc cgl 2016     | ssc cgl 07 09 2016     | time and work     | quantitative aptitude     | Add Bounty

A and B together can complete a work in 24 days. B alone does 1/3rd part ofthis work in 12 days. How many days will A alone take to complete the remaining work?
1). 24
2). 36
3). 48
4). 72

SSC CGL Books


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |
option 3 is the correct answer as per the answer key

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+4)
Submit:

Other Questions

1. Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. The ratio between the capacity of a man and a woman is

2. 7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

3. 20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men Joined them. In how many more days is the work completed ?

4. Running at the same constant rate, 6 identical machines can produce a total of 270 balls per 3 minutes. At this rate, how many balls could 10 such machines produce in 2 minutes?

5.  A works twice as fast as B. if both of them can together finish a piece of work in 12 days, then B alone can do it in

6. Direction: Vivek works ‘p’ hours a day and rests ‘b’ hours a day. This pattern continues for 1 week, with an exactly opposite pattern next week, and so on for six weeks. Every 7th week he has a different pattern. When he works longer than he rests, his wage per hour is 50% mo

7.  A can do 1/4th part of the work in 10 days, B can do 40% of the work in 40 days and C can do 1/3rd of the work in 13 days. Who will complete the work first?

8. Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?

9.  A can finish a work in 12 days and B can finish the same work in 24 days. How many days will they take to finish the work together ?

10.  36 workers can reap a field in 6 days. If the work is to be completed in 4 days, the extra workers required are