P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?
1). 9 days
2). 27 days
3). 36 days
4). 18 days
Let the total work is 60 units
P can do it in 60 days i.e. 1 unit work per day
Q can do it in 30 days i.e. 2 unit work per day
If both work together 3 units work can be don in a day.
90% of total work is 0.9 * 60 = 54 units.
54 units work can be done by both P & Q = 54 / 3 = 18 days.