P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?

Asked on by | Votes 28 | Views: 800 | Tags: ssc     | ssc chsl     | ssc chsl tier 1     | ssc chsl 2017     | ssc chsl 31 01 2017     | time and work     | quantitative aptitude     | Add Bounty

P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?
1). 9 days
2). 27 days
3). 36 days
4). 18 days

SSC CGL Books


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

22 vote
Answered by on | Votes 22 |

Let the total work is 60 units

P can do it in 60 days i.e. 1 unit work per day

Q can do it in 30 days i.e. 2 unit work per day

If both work together 3 units work can be don in a day.

90% of total work is 0.9 * 60 = 54 units.

54 units work can be done by both P & Q = 54 / 3 = 18 days.

Accepted Answer

Join Telegram Group




Other Questions

1. A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

2.  A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

3.  If A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in

4.  Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

5. If 40 men working 8 hours per day can complete a complete a project in 21 days. How many hours per day must 48 men work to complete the same project in 7 days?

6. A tank can be filled by two taps X and Y in 5 hrs and 10 hrs respectively while another tap Z empties the tank in 20 hrs. In how many hours can be tank be filled, if all 3 taps are kept open?

7.  Some persons can do a piece of work in 12 days. Two times the number of these people will do half of that work in?

8.  25 men can complete a work in 8 days. 15 women can complete the same work in 20 days & 9 children can complete it in 40 days. In how many days can one man, one woman and one child together complete th

9. Mehdi can complete a work in 25 hours. If he is joined by Jahnavi who is 50% more efficient, in what time will they together finish the work?

10. P and Q can do a project in 20 and 12 days respectively. In how many days can they complete 40% of the project if they work together?