A does 75% of a work in 25 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?

Asked on by | Votes 0 | Views: 127 | Tags: ssc     | ssc chsl     | ssc chsl tier 1     | ssc chsl 2016     | ssc chsl 15 01 2017     | time and work     | quantitative aptitude     | Add Bounty

A does 75% of a work in 25 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?
1). 50 days
2). 80 days
3). 24 days
4). 37.5 days

SSC CGL Books


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |
50 days : seems correct

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+2)
Submit:

Other Questions

1.  A is twice efficient as B and together they do the same work in as much time as C and D together. If C and D can complete the work in 20 and 30 daysrespectively, working alone ,then in how many days A

2. A can do a work in 20 days and B in 10 days. If they work on it together for 5 days, then what fraction of work is left.

3. R is 80% more efficient than S. If S alone can make a book in 90 days, then R alone can make the book in how many days?

4. A is twice as good as B and together they finish a piece of work in 48 days. What is the number of days taken by A alone to finish the work?

5. A and B can do a work in 45 days and 40 days respectively. They began the work together but A left after some time and B completed the remaining work in 23 days. After how many days of the start of the work did A leave ?

6. A, B and C can finish a work in 20, 30 and 60 days respectively working alone. If A and B started working together and after 5 days, B left the work and C joined to finish the remaining work with A. How many days did C work?

7.  A is thrice good a workman as B and therefore is able to finish a job in 60 days less than B. Working together they can do it in?

8.  If 6 man & 8 woman can do a piece of work in 10 days while 26 men & 48 women can do the same work in 2 days . In how many days 15 men & 20 women will do the same work?

9. Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?

10. A, B and C can do a job working alone in 12, 16 and 24 days respectively. In how many days they can do the job if they worked together?