Asif is twice as good as workman as Bashir and together they finish a piece of work in 30 days. In how many days will Asif alone finish the work?

Asked on by | Votes 1 | Views: 262 | Tags: time and work     | quantitative aptitude     | Add Bounty

Asif is twice as good as workman as Bashir and together they finish a piece of work in 30 days. In how many days will Asif alone finish the work?
1). 90
2). 45
3). 60
4). 75


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

1 vote
Answered by on | Votes 1 |

Efficiency ratio of Asif and Bashir = 2 : 1

So, Ratio of time taken by Asif and Bashir = 1 : 2

Let Asif finish the work in x days and Bashir finish the same work in 2x days

According the question,

1/x + 1/2x = 1/30

⇒ 3/2x = 1/30

⇒ x = 3/2 × 30

⇒ x = 45 days

∴ Asif will alone finish the work in 45 days

Join Telegram Group




1 vote
Answered by on | Votes 1 |

Efficiency ratio of Asif and Bashir = 2 : 1

So, Ratio of time taken by Asif and Bashir = 1 : 2

Let Asif finish the work in x days and Bashir finish the same work in 2x days

According the question,

1/x + 1/2x = 1/30

⇒ 3/2x = 1/30

⇒ x = 3/2 × 30

⇒ x = 45 days

∴ Asif will alone finish the work in 45 days




Answer This Question

Name:
Email:
Answer :
Sum of (5+5)
Submit:

Other Questions

1. A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work ?

2.  If 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is :

3.  A can do a piece of work in 1o days, B can do the same work in 15 days. They work for 5 days. The rest of work finished by C in 2 days. If they get Rs 1500 for the whole work, the daily wages of B and

4. A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

5. 3 girls can do a piece of work in 8 days, 3 boys can do the same piece of work in 9 days, 7 men do the same piece of work in 3 days and 6 women can do the same piece of work in 4 days. Who is the most efficient?

6. 5 men can make 1000 similar articles in 18 days. 20 women can do the same work in 6 days and 15 children can do it in 10 days. 12 men, 10 women and 5 children worked for 3 days for making 1000 articles of same kind. If the remaining work is to be completed by women only in 1 day, how many women will be required?

7. If a work can be completed by 96 boys or 36 men in 20 days, the number of days required to complete the work by 8 boys and 12 men is

8. Two labourers A and B are paid a total of Rs. 650 per day. If A is paid 160 percent of what is paid to B, how much (in Rs.) is B paid?

9. A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs. 960 far the whole work how much money A gets ?

10. Anil is twice as good as workman as Bimal and together they finish a piece of work in 9 days. In how many days will Anil alone finish the work?