Aman alone can do a piece of work in 6 days and Bijoy alone in 8 days. Aman and Bijoy undertook to do it for Rs. 3200. With the help of Chinmesh, they completed the work in 3 days. Compute the money to be paid to Chinmesh?

Asked on by | Votes 0 | Views: 23 | Tags: time and work     | quantitative aptitude    

Aman alone can do a piece of work in 6 days and Bijoy alone in 8 days. Aman and Bijoy undertook to do it for Rs. 3200. With the help of Chinmesh, they completed the work in 3 days. Compute the money to be paid to Chinmesh?
1). Rs. 750
2). Rs. 600
3). Rs. 400
4). Rs. 800

Answer This Question with Explaination and Earn! Click Here to Know More!


Share on Facebook      Share on Whatsapp       Share on Twitter




0 answers

Answer This Question

Name:
Email:
Answer :
Sum of (1+3)
Submit:

Other Questions

1.  A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?

2. A & B together finish a job in 24 days, while A, B & C together can finish the same job in 8 days. C alone will finish the job in

3. A and B can complete a piece of work in 15 days and 10 days respectively. They contracted to complete the work for Rs. 30,000. The share of A in the contracted money will be :

4. P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?

5. If Kavita is 70% more efficient than Savita and 50% less efficient than Babita, Savita is what percent less efficient than Babita?

6. A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs. 960 far the whole work how much money A gets ?

7. If 12 men working 8 hours a day complete the work in 10 days, how long would 16 men working $7\frac{1}{2}$ hours a day take to complete the same work ?

8.  A man is paid 20 for each day he works and forfeits 3 for each day he is idle. At the end of 60 days he gets 280. Then, he was idle for

9. If two pipes P and Q are such that, they can fill a large tub in 6 and 18 minutes respectively. They are opened on alternate minutes. Find in how many minutes, the tub shall be full?

10. A man and a woman working together can do a certain work in 18 days. Their skills in doing the work are in the ratio 3:2. many days will the woman take to finish the work alone?