 A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?

Asked on by | Votes 19 | Views: 208 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?

A). 81

B). 82

C). 83

D). 84


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

20 vote
Answered by on | Votes 20 |

83



NA

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+4)
Submit:

Other Questions

1. Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. The ratio between the capacity of a man and a woman is

2. Two pipes A and B, would fill a cistern in 20 and 30 minutes respectively. Both pipes being opened, find when the second pipe must be turned off so that the cistern may be just filled in 14 minutes?

3. A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

4.  An empty pipe can empty 1/4 of a cistern in 15 minutes. In 5 minutes, what part of the cistern will be emptied ?

5.  A certain number of men can do a work in 20 days. If there were 4 more men, they. would finish it in 4 days less. How many men are there ?

6.  A and B can do a piece of work in 60 days and 40 days respectively. They started the work together but after some days, A left the work. B alone did the remaining work in 20 days. Find after how many

7.  A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage,

8.  A and B can do a work in 12 days and 36 days respectively. If they work on alternate days beginning with B, in how many days will the work be completed?

9. Manjeet can do a work in 18 hours. If he is joined by Jaya who is 100% more efficient, in what time will they together finish the work?

10. P and Q can do a project in 6 and 12 days respectively. In how many days can they complete 25% of the project if they work together?