P, Q and R contract to do a work for Rs. 1650, P can do a work in 8 days, Q can do a work in 12 days and R can do a work in 15 days, then find the share of R?
1). Rs. 400
2). Rs. 420
3). Rs. 800
4). Rs. 350
Let the total work be 120 units(LCM of 8, 12 and 15)
⇒ One day work of P = 15 units
⇒ One day work of Q = 10 units
⇒ One day work of R = 8 units
P, Q and R contract to do a work for Rs. 1650
∴ Share of R = 8/33 × 1650 = Rs. 400