 A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished he remaining work. In how many days A alone can finish the job?

Asked on by | Votes 0 | Views: 118 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished he remaining work. In how many days A alone can finish the job?

A). 60 days

B). 40 days

C). 20 days

D). 17 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

60 days



A + B ‘s 1 day’s work = 1/30 

Their 20 day’s work = 1/30 × 20 = 2/3 

Remaining work = 1/3 

1/3 of the work is done by A in 20 days. 

Then, whole work can be done by A in 3 × 20 = 60 days.

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+4)
Submit:

Other Questions

1. A can finish a work in 30 days working 16 hours a day. B can finish the same work in (80/3) days working 18 hours a day. Find in how many days A and B together can finish the same work, if A and B work 20 hours a day?

2. A group of men started work and aimed to finish the same in 10 days. After 4 days, 6 men left. The remaining men finished the work in 12 more days. How many men were there in the group initially?

3.  Ronald and Elan are working on an assignment. Ronald takes 6 hrs to type 32 pages on a computer, while Elan takes 5 hrs to type 40 pages. How much time will they take, working together on two differen

4. A and B do ($\frac{3}{5}$)th part of a work and the rest of the work is completed by C. If A, B and C take the same work for Rs 5000, then what is the share of C (in Rs)?

5.  Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two differ

6. Amar started doing a work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?

7.  A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take t

8. Imran can do a piece of work in 12 days, while Hashim can do the same in 36 days and Rajat in 18 days. If Imran is assisted by Hashim and Rajat respectively on alternate days, then find the number of days in which the work will be finished.

9.  A man, a woman and a boy can together complete a piece of work in 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman take to complete the work?

10. A and B can separately do a piece of work in 6 days and 12 days respectively. How long will they together take to do the work?