A is three times as efficient as B and takes 60 days less than B for doing a job. The time in which they can do it together is?

Asked on by | Votes 0 | Views: 65 | Tags: time and work     | quantitative aptitude     | Add Bounty

A is three times as efficient as B and takes 60 days less than B for doing a job. The time in which they can do it together is?
1). 15 days
2). 30 days
3). \(22\frac{1}{2}days\)
4). 60 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

Let the number of days in which B does a job be x.

Given, A is three times as efficient as B and takes 60 days less than B for doing a job.

Number of days in which A finishes the job = x – 60

In 1 day, B finishes 1/x of the work.

∴ A finishes 3/x of the work in 1 day.

Thus, A will finish the work in x/3 days.

⇒ x/3 = x – 60

⇒ 2x/3 = 60

⇒ x = 90 days

Thus, B finishes the work in 90 days, while A finishes it in 30 days.

Working together in 1 day, they finish part of work = 1/90 + 1/30

Thus they will finish the work in number of days = 90/4 = $(22\frac{1}{2}days)$

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+4)
Submit:

Other Questions

1. A can finish a work in 18 days and B can do the same work in 5 days. B worked for 10 days and left the Job. In how many days, A alone can finish the remaining work?

2. A man and a boy received Rs.800 as wages for 5 days for the work they did together. The man's efficiency in the work was three times that of the boy. What are the daily wages of the boy ?

3. Nirmit can do $\frac{2}{3}$ of a job in 18 days. Kashish is twice as efficient as Nirmit. In how many days Kashish will complete the job?

4. A and B together can do a piece of work in 12 days which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In how many days B could finish the work ?

5.  Twelve men can complete a piece of work in 32 days. The same work can be completed by 16 women in 36 days and by 48 boys in 16 days. Find the time taken by one man, one woman and one boy working toget

6. A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the Job is

7. A can do a piece of work in 18 days.He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

8.  A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in

9.  45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete that work working 10 hours a day ?

10. A, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?