A is three times as efficient as B and takes 60 days less than B for doing a job. The time in which they can do it together is?
1). 15 days
2). 30 days
3). \(22\frac{1}{2}days\)
4). 60 days
Let the number of days in which B does a job be x.
Given, A is three times as efficient as B and takes 60 days less than B for doing a job.
Number of days in which A finishes the job = x – 60
In 1 day, B finishes 1/x of the work.
∴ A finishes 3/x of the work in 1 day.
Thus, A will finish the work in x/3 days.
⇒ x/3 = x – 60
⇒ 2x/3 = 60
⇒ x = 90 days
Thus, B finishes the work in 90 days, while A finishes it in 30 days.
Working together in 1 day, they finish part of work = 1/90 + 1/30
Thus they will finish the work in number of days = 90/4 = $(22\frac{1}{2}days)$