A can finish a work in 18 days and B can do the same work in 5 days. B worked for 10 days and left the Job. In how many days, A alone can finish the remaining work?

Asked on by | Votes 0 | Views: 44 | Tags: time and work     | quantitative aptitude     | ssc cgl tier 1 2013     | Add Bounty

A can finish a work in 18 days and B can do the same work in 5 days. B worked for 10 days and left the Job. In how many days, A alone can finish the remaining work?
1). 6 days
2). $5\frac{1}{2}$ days
3). 5 days
4). 8 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |
6 days : - is correct hence option 1

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+3)
Submit:

Other Questions

1. 2 men and 1 woman together can complete a piece of work in 14 days, while 4 women and 2 men together can do it in 8 days. If a gets Rs. 600 per day. how much should a woman get per day ?

2.  Two persons, Rahul and Manoj, undertake a work for Rs. 9000. Rahul alone can do the work in 16 days and Manoj alone can do it in 24 days. If, with the assistance of a third person Niraj, they finish t

3. Kamal can do a work in 20 days. Bimal is 20% more efficient than Kamal. Suresh is 25% more efficient than Bimal. The number of days, Suresh will take to do the same piece of work, is

4. Ashley is twice as good as Jake and together they complete a piece of work in 20 days. In how many days will Ashley alone finish the work? 

5. A contractor undertook to finishn a work in 92 days and employed 110 men. After 48 days, he found that he had already done $\frac{3}{5}$ part of the work,the number of men he can withdraw so that the work may still be finished in time is:

6. If 20 men can build a wall 25 meters long in 4 days, what length of a similar wall can be built by 30 men in 6 days?

7. Mehdi can complete a work in 25 hours. If he is joined by Jahnavi who is 50% more efficient, in what time will they together finish the work?

8. Makarand works 2 times as fast as Samarjit. If Samarjit can complete a job alone in 27 days, then in how many days can they together finish the job?

9. A and B can together finish work in 30 days. They worked at it for 20 days and then B left. The remaining work was done by A alone in 20 more daysA alone can finish the work in

10. Two pipes X and Y can fill an empty tank in 16 hours and 20 hours respectively. Pipe Z alone can empty the completely filled tank in 25 hours. Firstly both pipes X and Y are opened and after 6 hours pipe Z is also opened. What will be the total time (in hours) taken to completely fill the tank?