A and B get a work to be done for Rs. 30960. A and B can finish the work in 18 days and 24 days respectively. But they need help to finish the work in 8 days so they called C. Find C’s salary?

Asked on by | Votes 0 | Views: 74 | Tags: time and work     | quantitative aptitude     | Add Bounty

A and B get a work to be done for Rs. 30960. A and B can finish the work in 18 days and 24 days respectively. But they need help to finish the work in 8 days so they called C. Find C’s salary?


1). Rs. 6820
2). Rs. 6860
3). Rs. 6840
4). Rs. 6880


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

Time taken by A = 18 days

Time taken by B = 24 days

Time taken by A, B and C = 8 days

Let Total work = LCM of 18, 24 and 8 = 72 units

Efficiency of A = 72/18 = 4 units/day

Efficiency of B = 72/24 = 3 units/day

Efficiency of A, B and C together = 72/8 = 9 units/day

Efficiency of C = Total efficiency - Efficiency of (A + B)

Efficiency of C = 9 - (4 + 3) = 9 - 7 = 2 units/day

Work done by C = 2 × 8 = 16 units

For 72 units they get = Rs. 30960

1 unit = Rs. 430

∴ C’s salary = 16 × 430 = Rs. 6880

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+3)
Submit:

Other Questions

1. A tank has a leak at bottom which would empty it in 24 hours. A tap is turned on which fills 50 litres/hour, the tank now fills in 12 hours. How many litres does the tank hold?

2. 3 men and 7 women can do a Job In 5 days, while 4 men and 6 women can do it in 4 days. The number of days required for a group of 10 women working together, at the same rate as before, to finish the same job is :

3. 3 men or 4 women can complete a job in 120 days. 12 men and 16 women will complete the same job in how many days?

4. Mayur can complete a work in 27 hours. If he is joined by Jayantika who is 100% more efficient, in what time will they together finish the work?

5. A can make a cupboard in 10 days and B can do it in 50 days. Along with C, they did the job in 6.25 days only. Then in how many days C alone can do the job?

6. The ratio of efficiencies of P, Q and R is 4 : 3 : 8. In how much time can they finish a work together if Q can finish it alone in 4.5 hours? (in minutes)

7.  X can do a work in 16 days. In how many days will the work be completed by Y, if the efficiency of Y is 60% more than that of X?

8.  11 men and 8 women can earn Rs. 16120 in 13 days. 9 men and 15 women can earn Rs. 11160 in 8 days. In how many days can 16 men and 12 women earn Rs. 10920 ?

9. If 6 men working 8 hours a day earn Rs. 1680 per week, then 9 men working 6 hours a day will earn per week:

10. 5 men and 2 women working together can do four times as much work per hour as a man and a woman together. The work done by a man and a woman should be in ratio :