3 men and 7 women can do a Job In 5 days, while 4 men and 6 women can do it in 4 days. The number of days required for a group of 10 women working together, at the same rate as before, to finish the same job is :

Asked on by | Votes 0 | Views: 59 | Tags: time and work     | quantitative aptitude     | ssc cpo 2013     | Add Bounty

3 men and 7 women can do a Job In 5 days, while 4 men and 6 women can do it in 4 days. The number of days required for a group of 10 women working together, at the same rate as before, to finish the same job is :
1). 30 days
2). 36 days
3). 40 days
4). 20 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |
option 4 is the right answer

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+4)
Submit:

Other Questions

1. Rohit can distribute all morning newspaper in 32/9 hours but with the assistance of his brother, the newspaper were distributed in 32/15 hours. In how many hours, his brother alone can distribute all morning newspaper?

2. A teacher works twice as fast as a student. If a student can complete 1/12th part of the work in a day, the number of days in which the teacher and the student can together finish the work is;

3. A swimming pool has 3 pipes to drain off the water. The first two pipes A and B, operating simultaneously, can empty the pool in 9/16 the time than that taken by C alone. Pipe A, working alone, takes one third the time taken by pipe B. All of them together take 2 hrs 24 minutes to empty the pool. Time taken by pipe A to empty the pool in hours is

4. Pipe A, B and C can fill a cistern in 12, 24, 48 hrs respectively. If all the pipes are opened simultaneously, Find the time when the pipe B must be turned off, so that the cistern may be just filled in 8 hrs?

5. A can finish a work in 30 days working 16 hours a day. B can finish the same work in (80/3) days working 18 hours a day. Find in how many days A and B together can finish the same work, if A and B work 20 hours a day?

6. P and Q undertook to do a work for Rs. 7200. P alone could do it in 20 days and Q alone in 12 days. With the assistance of R they finished the work in 5 days. What is the share (in Rs) of R?

7. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it ?

8.  A and B can do a job in 10 days. B and C can do the same job in 15 days. If all three worked together complete the work in 6 days, then in how many days can B complete the whole job?

9. Amar is 2 times as good a workman as Badal and therefore is able to finish a job in 15 days less than Badal. In how many days can they together complete the job?

10.  8 boys complete a work in 14 days . In how many days will 14 boys complete that work?