4 men can build a small house in 12 days. How long would it take for 6 men to build the same house?

Asked on by | Votes 34 | Views: 293 | Tags: time and work     | quantitative aptitude     | Add Bounty

4 men can build a small house in 12 days. How long would it take for 6 men to build the same house?


1). 9 days
2). 8 days
3). 8.1 days
4). 8.2 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

21 vote
Answered by on | Votes 21 |

Time taken by 4 men to build a small house = 12 days

⇒ Time taken by one man to build a small house = 12 × 4 = 48 days

⇒ Time taken by 6 men to build the same house = 48/6 = 8 days

∴ Time taken by one man to build the same house = 8 days

Accepted Answer

Join Telegram Group




Other Questions

1.  A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in

2. A can complete $\frac{2}{3}$ of a work in 4 days and B can complete $\frac{3}{5}$ of the work in 6 days. In how many days can both A and B together complete the work ?

3.  56 men completes a work in 12 days. How many men will be required to complete the work in 16 days?

4. A can do a certain job in 36 days. When A and B work together, they can do the same job in 9 days. Thus, B is: 

5.  A and B can do a piece of work in 12 days; B and C can do it in 15 days and C and A can do it in 20 days. A alone can do the work in:

6.  A can do a piece of work in 15 days and B in 20 days. They began the work together but 5 days before the completion of the work, A leaves. The work was completed in?

7. Three persons started to complete a project for Rs. 1,600. The first person can complete the project in 8 days, the second person in 12 days and the third person in 16 days. They complete the project together with the help of a fourth person in 3 days. What will the fourth person get?

8. If 12 furnaces consume 13 tonnes of coal in \(6\frac{1}{2}\) hours, how long will 7 furnaces be consuming 14 tonnes?

9.  If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be?

10. P and Q can do a project in 6 and 12 days respectively. In how many days can they complete 25% of the project if they work together?