12 men or 30 boys can complete a work in 72 days. How many days will 48 men and 24 boys will take to complete the same work?
1). 20
2). 18
3). 15
4). 25
We have,
Efficiency of 12 men = Efficiency of 30 boys
⇒ Efficiency of 2 men = Efficiency of 5 boys
⇒ Efficiency of 48 men = Efficiency of 120 boys
Now, we have of find out time taken by 48 men and 24 boys to complete the work or 144(120 + 24) boys to complete the works
Now,
Total work = time taken × number of workers = 72 × 30 = 2160
⇒ Time taken by 144 boys to complete the work = Total work/no. of workers = 2160/144 = 15 days
∴ 48 men and 24 boys take 15 days to complete the work