A pump can fill a tank with water in 3 hours. Because of a leak it took \(3\frac{1}{5}hours\) to fill the tank. The leak can drain all the water in the tank in

Asked on by | Votes 0 | Views: 43 | Tags: time and work     | quantitative aptitude     | Add Bounty

A pump can fill a tank with water in 3 hours. Because of a leak it took \(3\frac{1}{5}hours\) to fill the tank. The leak can drain all the water in the tank in
1). 54 hours
2). 36 hours
3). 42 hours
4). 48 hours


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

The pump can fill the tank in 3 hours

∴ Part of tank filled by the pump in 1 hour = 1/3

Let, the leak can drain all the water in ‘x’ hours

∴ Part of tank leaked by the drain in 1 hour = 1/x

Given, Because of a leak pump took $(3\frac{1}{5}hours = \frac{{16}}{5}hours)$ to fill the tank

$(\therefore \frac{1}{3} \times \frac{{16}}{5} - \frac{1}{x} \times \frac{{16}}{5} = 1)$

⇒ 16/15 - 16/5x = 1

⇒ 16/5x = 16/15 – 1 = 1/15

⇒ 5x = 16 × 15

⇒ x = 48 hours

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+4)
Submit:

Other Questions

1.  A and B together can plough a field in 10 hours but by himself A requires 15 hours. How long would B take to plough the same field?

2. Three persons undertake to complete a piece of work for Rs. 1,200. The first person complete the work in 8 days, second person in 12 days and third person in 16 days.They complete the work with the help of a fourth person in 3 days. What does the fourth person get?

3. 4 men can complete a piece of work in 3 days. 6 women can complete the same piece of work in 3 days, whereas 3 children can complete the same piece of work in 8 days. 3 women and 4 children worked together for 1 day. If only men were to finish the remaining work in 1 day, how many total men would be required?

4.  9 men working 7 hours a day can complete a piece of work in 15 days. How many days can 6 men working for 9 hours a day, complete the same piece of work?

5. Two taps can fill a tank in 12 minutes and 15 minutes respectively. Third tap can empty the tank in 6 minutes. Both the taps are opened for 5 minutes and after that the third tap is also opened. In how many minutes will the tank be emptied?

6. A certain number of men can do a piece of work in 45 days. If there were 6 men more, the work can be finished 18 days earlier. The number of men working is

7.  The wages for 27 women amount to Rs 12000 in 8 days. How many men must work for 6 days to receive Rs 8000? The daily wages of a man is double that of a woman.

8. X and Y can do a work in 20 days, Y and Z can do the same work in 15 days, Z and X can do the same work in 12 days. The time taken by X, Y and Z to do the same work it

9.  A can do piece of work in same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days then B alone could do it in?

10.  15 labourers complete a work in 10 days working 6 hours per day. If 18 labourers are employed on that work and the work is to be completed in 5 days then how many hours per day the work should be cont