 A can do piece of work in same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days then B alone could do it in?

Asked on by | Votes 21 | Views: 157 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can do piece of work in same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days then B alone could do it in?

A). 15

B). 20

C). 25

D). 30


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

24 vote
Answered by on | Votes 24 |

25



(A+B )’s one day

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+2)
Submit:

Other Questions

1.  A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?

2.  A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C work together, they will complete the work in?

3. A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for :

4. Three men can complete a piece of work in 6 days. Two days after they started the work. 3 more men Joined them. How many days will they take to complete the remaining work ?

5. A tank can be filled using pipe A and emptied using pipe B. Pipe B can empty the tank in 12 hrs. When both the pipes are simultaneously opened, the tank is half full in 2 hrs. In how much time can pipe A fill the tank alone?

6.  A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

7.  A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in

8.  A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in

9. A, B and C can finish a job working alone in 72, 24 and 36 days respectively. In how many days they can finish the job if they worked together?

10.  A and B can do a job together in 7 days. A is 1 ¾ times as efficient as B. the same job can be done by A alone in: