ExamCompetition Forum Question Papers Ask A Question Mock Test Learn & Earn Sign Up Login Menu



25 vote

Three people A, B and C working individually can finish a job in 10, 12 and 20 days respectively. They decided to work together but after 2 days, A left the work and after another one day, B also left work. If they got two lacs collectively for the entire work, find the difference of the highest and lowest share

Asked on by | Votes 25 | Views: 2291 | Tags: time and work     | quantitative aptitude     | Add Bounty

Three people A, B and C working individually can finish a job in 10, 12 and 20 days respectively. They decided to work together but after 2 days, A left the work and after another one day, B also left work. If they got two lacs collectively for the entire work, find the difference of the highest and lowest share


1). 40000
2). 70000
3). 75000
4). 81000


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

11 vote
Answered by on | Votes 11 |

Let the total work be LCM(10, 12, 20) = 60 units

⇒ Efficiency of A = 60/10 = 6 units/day

⇒ Efficiency of B = 60/12 = 5 units/day

⇒ Efficiency of C = 60/20 = 3 units/day

Since the number of working days are different for each person, the share of each will be calculated in the ratio of the units of work done

Now, A works for 2 days and B works for 3 days

⇒ Work done by A = 2 x 6 = 12 units

⇒ Work done by B = 3 x 5 = 15 units

⇒ Work done by C = 60 – 12 – 15 = 33 units

Therefore, ratio of work done = 12 : 15 : 33 = 4 : 5 : 11

⇒ A’s share = (4/20) x 2,00,000 = Rs 40,000

⇒ B’s share = (5/20) x 2,00,000 = Rs 50,000

⇒ C’s share = (11/20) x 2,00,000 = Rs 1,10,000

Difference of the highest and lowest share = Rs 1,10,000 – 40,000 = Rs 70,000

∴ Difference is of Rs. 70000

Accepted Answer

Join Telegram Group




Other Questions

1.  If 4 men can colour 48 m long cloth in 2 days, then 6 men can colour 36 m long cloth in

2. A can finish a work in 18 days and B can do the same work in 5 days. B worked for 10 days and left the Job. In how many days, A alone can finish the remaining work?

3. A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?

4.  X men can do a work in 120 days. If there were 20 men less, the work would have taken 60 days more. What is the value of X?

5. 3 men or 7 women can do a piece of work in 32 days. The number of days required by 7 men and 5 women to do a piece of work twice as large is

6.  A man, a woman and a boy can complete a job in 3 days, 4 days and 12 days respectively. How many boys must assist 1 man and 1 woman to complete the job in 1/4th of a day?

7. X is 3 times as fast as Y and is able to complete the work in 40 days less than Y. Then the time in which they can complete the work together is

8.  A person P takes 4 hrs time to complete a job and Q takes 6 hrs to complete the same job if they work together how much time will they require to complete the job?

9. A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How, many persons were originally there ?

10.  A and B can finish a piece of work in 30 days. They worked at it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in