Two pipes A and B together can fill a cistern in 4 hours. Had they been opened separately, then B would take taken 6 hours more than A fill the cistern. How much time will be taken by A to fill the cistern separately?

Asked on by | Votes 0 | Views: 36 | Tags: time and work     | quantitative aptitude     | Add Bounty

Two pipes A and B together can fill a cistern in 4 hours. Had they been opened separately, then B would take taken 6 hours more than A fill the cistern. How much time will be taken by A to fill the cistern separately?
1). 6 hours
2). 8 hours
3). 10 hours
4). 12 hours


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

3 vote
Answered by on | Votes 3 |

⇒ Let the cistern be filled by pipe A alone in x hours.

⇒ Then, pipe B will fill it in (x + 6) hours

⇒ 1/x + 1/(x + 6) = ¼ (x + 6 + x)/(x (x + 6)) = 1/4

⇒ x2 - 2x - 24 = 0 (x - 6) (x + 4) = 0

⇒ x = 6, - 4 [Ignoring the -ve value of x]

X = 6 hours will be the required ans.

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1. 7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

2.  A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?

3.  A works alone, he would take 4 days more to complete the job than if both A and B worked together. If B worked alone, he would take 16 days more to complete the job than if both A and B work together.

4.  A and B can do a piece of work in 12 days. B and C can do it in 15 days. A and C can do the same piece of work in 20 days. In how many days can A, B and C each finish the same work independently ?

5. 8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. in how many days would the remaining work be completed ?

6.  A can do a work in 9 days and B can do the same work in 18 days. If they work together, in how many days will they complete the work?

7. Twenty women together can complete a work in 16 days, 16 men together can complete the same work in 15 days. The ratio of the working capacity of a men to that of a women is :

8. R is 80% more efficient than S. If S alone can make a book in 90 days, then R alone can make the book in how many days?

9.  A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

10. A is twice as good as B and together they finish a piece of work in 48 days. What is the number of days taken by A alone to finish the work?