 A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?

Asked on by | Votes 38 | Views: 4393 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?

A). 10 days

B). 20 days

C). 5 days

D). 4 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

27 vote
Answered by on | Votes 27 |

20 days



C = 1/2 - 1/4 - 1/5 = 1/20 => 20 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+3)
Submit:

Other Questions

1.  24 boys can finish a certain amount of food in 16 days. 32 Girls can finish the same amount of food in 24 days. 16 boys and 16 girls went on a camp with that fixed amount of food. After, 12 days some

2. C is 20% more efficient than A. A and B together can finish a piece of work in 16 days. B and C together can do it in 15 days. In how many days A alone can finish the same piece of work ?

3. X and Y can complete a work in 5 days. Y and Z can complete the same work in 6 days. Z and X can complete the same work in 15/2 days. In how many days will X, Y and Z together complete the work?

4. A and B working together, can do a piece of work in $4\frac{1}{2}$ hours, B and C working together can do it in 3 hours, C and A working together can do it in $2\frac{1}{4}$ hours. All of them begin the work at the same time. find how much time they will take to finish the piece of work.

5. A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day that was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job when they are making 36 more pieces per day?

6. A can do a work in 12 days and B in 24 days. If they work on it together for 4 days, then what fraction of work is left?

7.  A and B can together finish work in 30 days. They worked at it for 10 days together & then B left. The remaining work was done by A alone in 30 more days. B alone can finish the work in

8. 10 women can do a piece of work in 6 days, 6 men can do same work in 5 days and 8 children can do it in 10 days. What is the ratio of the efficiency of a woman, a man and a child respectively?

9. In each of the following questions, a question is followed by information given in three statements. You have to study the question alongwith the statements and decide the information given in which of the statement (s) is necessary to answer the question.

10. A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B and C finish it, working all together?