 A tank is normally filled in 18 hours but due to a leak in the bottom, it takes 3 hours more to fill completely. If the tank is filled completely, in what time will the leak empty it completely ?

Asked on by | Votes 0 | Views: 146 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A tank is normally filled in 18 hours but due to a leak in the bottom, it takes 3 hours more to fill completely. If the tank is filled completely, in what time will the leak empty it completely ?

A). 120 hours

B). 122 hours

C). 124 hours

D). 126 hours


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

126 hours



Let the time taken by the leak in emptying the tank be 1 hours.
In one hour, the pipe can fill 1/18 part of the tank and the leak can empty 1/x part of the tank. 
∴ part of the tank filled in 1 hour
= 1/18 - 1/x = x-18/18x
So, it will be filled completely in 
1/(x-18/18x) hours = 18x/x-18 hours
∴ 18x/x-18 = 18 + 3 = 21
or 18x = 21x - 378
∴ x = 378/3 = 126 hours

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+1)
Submit:

Other Questions

1. A and B together can diga trench in 12 days, which A alone can dig in 28 days; B alone can dig it in

2.  A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

3. Samsung and Motorola companies together can manufacture 32 Cell phones in 4 days. After 8 days, Motorola Stopped manufacturing. Samsung took 12 more days to manufacture rest of the cell phones. If total of 100 cell phones were manufactured, the time taken by Motorola to manufacture 15 Cell phones is

4.  18 women can complete a work in 12 days and 12 men can complete the same work in 9 days. In how many days will 8 men and 8 women complete that work?

5.  A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days?

6. A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

7. A can work 6 times faster than B and takes 40 days less than B to complete the work. In how many days does A and B individual can complete the work?

8. A and B together do a job in 15 days and A alone could do the same job in 20 days. How many days would B take to do half the job if he worked alone?

9.  A takes 10 hours to do a work. B takes 12 hours to do the same works. In how many hours A & B working together will complete the work?

10.  If 3 persons can do 3 times of a particular work in 3 days, then, 7 persons can do 7 times of that work in