 Two men and three women working 7 hours a day finish a work in 5 days. Four men and four women working 3 hours a day complete the work in 7 days. The number of days in which only 7 men working 4 hours

Asked on by | Votes -1 | Views: 1890 | Tags: quantitative aptitude     | time and work     | Add Bounty

 Two men and three women working 7 hours a day finish a work in 5 days. Four men and four women working 3 hours a day complete the work in 7 days. The number of days in which only 7 men working 4 hours

A). 5 days

B). 6 days

C). 7 days

D). 10 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

5 days



2M + 3W ----- 35 h

4M + 4W ------- 21 h

7M -------? d

70M + 105W = 84M +84M

21W = 14M => 2M = 3W

4 * 35 = 7 * x => x = 20 hours

20/4 = 5 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+1)
Submit:

Other Questions

1. .A can finish a work in 7 days . B can finish the same work in 9 days . The days required to finish the work by both of them together.

2. If A is 6 times more than B, then by what percentage is B is less than A?

3. A and B can separately do a piece of work in 6 days and 12 days respectively. How long will they together take to do the work?

4. Two pipes P and Q can fill an empty tank in 40 min and 20 min respectively. R can empty a full tank in 30 minutes. If all three are opened together, how much time will they take to empty/fill the tank?

5. Rancho is 50% more efficient than Sundar. Rancho does a work in 4 days. In how many days will Rancho and Sundar finish a work if first day Rancho works alone, second day Sundar works alone and after that they work together?

6. If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similarr type of wall of length 100 m ?

7. A and B together can do a piece of work in 20 days and A alone can do it in 30 days. B alone can do the work in how many days?

8. 12 men and 1 woman can complete a piece of work in 14 days while 4 women and 2 men can do the same work in 8 days. If a man gets Rs. 180 per day. then a woman will get per day

9. A can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job ?

10.  A and B can do a work in 4 hours and 12 hours respectively. A starts the work at 6 AM and they work alternately for one hour each. When will the work be completed?