 A and B can do a piece of work in 60 days and 40 days respectively. They started the work together but after some days, A left the work. B alone did the remaining work in 20 days. Find after how many

Asked on by | Votes 0 | Views: 89 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A and B can do a piece of work in 60 days and 40 days respectively. They started the work together but after some days, A left the work. B alone did the remaining work in 20 days. Find after how many

A). 10 days

B). 12 days

C). 14 days

D). 16 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

12 days



Number of days = (40 - 20) x 60/60 + 40

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1. How many men need to be employed to complete a Job in 5 days, if 15 men can complete $\frac{1}{3}$ of the job in 7 days ?

2. Work done by (x + 4) men in (x + 5) days is equal to the work done by (x – 5) men in (x + 20) days. Then the value of x is

3. 6 men or 12 women can do a piece of work in 20 days. In how many days can 8 men and 16 women do twice as big as this work ?

4. A company employed 200 workers to complete a certain work in 150 days. If only one- fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was

5.  If 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is :

6. A and B can finish a job in 10 days while B and C can do it in 18 days. A started the job, worked for 5 days then B worked for 10 days and the remaining job was finished by C in 15 days. In how many days could C alone have finished the whole job?

7. Five women can do a work in thirty six days. If the ratio between the capacity of a man and a woman is 3 : 1, then find how may days it will take 5 men to complete the same work?

8. Two pipes P and Q can fill an empty tank in 40 min and 20 min respectively. R can empty a full tank in 30 minutes. If all three are opened together, how much time will they take to empty/fill the tank?

9. Two pipes A and B can fill an empty cistern in 8 hours and 10 hours respectively. If both the pipes are simultaneously opened in an empty cistern, what part of the cistern is filled after 4 hours?

10. Two labourers A and B are paid a total of Rs. 750 per day. If A is paid 150 percent of what is paid to B, how much (in Rs) is B paid?